Your browser does not support JavaScript!

COV ITRM Glossary

E

Estimate at Completion (EAC)

Definition

The expected total cost of a schedule activity, a work breakdown structure component, or the project when the defined scope of work will be completed. EAC is equal to the actual cost (AC) plus the estimate to complete (ETC) for all of the remaining work. EAC=AC plus ETC. The EAC may be calculated based on performance to date or estimated by the project team based on other factors, in which case it is often referred to as the latest revised estimate.


Reference:

PMBOK

Previous <  |  > Next
D < | > F