Early Start Date

Definition

In the critical path method, the earliest possible point in time on which the uncompleted portions of a schedule activity (or the project) can start, based on the schedule network logic, the data date, and any schedule constraints. Early start dates can change as the project progresses, and changes are made to the project management plan.


Reference:

PMBOK


See Also:

Early Finish Date (EF)