Crashing
Definition
A specific type of project schedule compression technique performed by taking action to decrease the total project schedule duration after analyzing a number of alternatives to determine how to get the maximum duration compression for the lease additional cost. Typical approaches for crashing a schedule include reducing schedule activity duration and increasing the assignment of resources on schedule activities.
Reference:
PMBOK