Schedule Network Analysis

(Context: General)

The technique of identifying early and late start dates, as well as early and late finish dates, for the uncompleted portions of project schedule activities. See also Critical Path Method, Program Evaluation and Review Technique, and Graphical Evaluation and Review Technique.

Reference:

PMBOK