Critical Path

Generally, but not always, the sequence of schedule activities that determines the duration of the project. Generally, it is the longest path through the project. However, a critical path can end, as an example, on a schedule milestone that is in the middle of the project schedule and that has a finish-no-later-than imposed date schedule constraint.

Reference:

PMBOK

Previous <  |  > Next
B < | > D
Enter your search query for glossary: